# 66--IRA - High-Temperature Chamber Furnace

Notice 1c49db41c3ed48d8a2b515db088a9727 (solicitation 89243327NEX000003) from ENERGY, DEPARTMENT OF, NATIONAL ENERGY TECHNOLOGY LABORATORY, posted 2026-11-10, responses due 2026-11-16T18:00:00.000Z. Status: open.

| Field | Value |
| --- | --- |
| Notice ID | 1c49db41c3ed48d8a2b515db088a9727 |
| Solicitation number | 89243327NEX000003 |
| Type | Sources Sought |
| Agency | ENERGY, DEPARTMENT OF |
| Sub-tier | ENERGY, DEPARTMENT OF |
| Office | NATIONAL ENERGY TECHNOLOGY LABORATORY |
| Posted | 2026-11-10T18:11:19.000Z |
| Response deadline (UTC) | 2026-11-16T18:00:00.000Z |
| Set-aside | - |
| NAICS | 333994 |
| PSC | 6640 |
| Place of performance | - |
| Award | - |

## Description

This amendment is to address several requests for clarifications associated with our Technical Specifications. Q1. Facility Access and Rigging: The specifications require installation at the R&D plateau on the NETL Pittsburgh site. Does the specific facility have a loading dock capable of receiving standard freight, and is there a clear, at-grade, or freight-elevator-accessible path to the final installation room with adequate door clearances for a 100 kW system? A1: NETL has a clear path to the final installation area with adequate door clearances for a 100 kW system. Q2. Utility Proximity: The furnace requires a 480-volt, three-phase, 60 Hz power supply supporting an overall power of at least 100 kW. Is the necessary hardwire drop or disconnect already existing within the immediate footprint of the intended installation area, or will the contractor be responsible for routing power from a distant sub-panel? A2: NETL is responsible for installing all necessary hardwire drops or disconnects. Q3. Gas Supply and Exhaust: The system requires a fueled incinerator torch to combust organic outgassing. Will the Government supply the necessary process and sweep gases (e.g, Argon, Nitrogen, Propane/Natural gas) via existing facility lines, and is there an existing facility exhaust or fume hood integration point for the torch output? A3: NETL is responsible for installing all necessary gases, gas lines, and venting lines. Q4. Lead Times and Compliance: Given that Brand Name or Equal highly customized vacuum furnaces built to NRTL, UL 508A, and NFPA 79 standards often have commercial lead times exceeding 6 to 9 months, will the anticipated RFQ allow for standard commercial lead times? Additionally, can you confirm if this procurement will be subject to the Trade Agreements Act (TAA) or strict Buy American Act (BAA) provisions? A4: NETL will accept standard commercial lead times for this procurement. This procurement will be subject to the FAR 52.225-5 Trade Agreements Act (TAA).

## Sources

- View on SAM.gov: https://sam.gov/opp/1c49db41c3ed48d8a2b515db088a9727/view
- Data as of 2026-11-14. Source: https://sam.gov/data-services/Contract%20Opportunities/datagov

## Cite this

"66--IRA - High-Temperature Chamber Furnace, SAM.gov contract opportunity 1c49db41c3ed48d8a2b515db088a9727." samgovapi.io, https://samgovapi.io/opportunity/1c49db41c3ed48d8a2b515db088a9727, data as of 2026-11-14. Primary record: https://sam.gov/opp/1c49db41c3ed48d8a2b515db088a9727/view

## API and MCP

- REST: GET https://samgovapi.io/api/v1/opportunities/1c49db41c3ed48d8a2b515db088a9727
- MCP tool: get_opportunity

Independent. Not affiliated with, endorsed by or sponsored by GSA, SAM.gov or any U.S. government agency. Registering in SAM.gov is free at sam.gov.

Get a free API key: https://samgovapi.io/sign-up?ref=ai-claudebot